Noreva, an energy market data and analytics provider (formerly Karbone Research), tracks the Western Interconnection as it moves from bilateral trading among dozens of standalone utilities to a footprint organized around two competing day-ahead markets, a binding regional resource adequacy program and an RTO that now spans two interconnections. The Western Electricity Coordinating Council (WECC) still counts about 38 balancing authorities across the Western Interconnection, with the California ISO alone balancing an estimated 35% of the region’s load (CAISO, “Balancing Authority,” accessed September 21, 2026). That count is starting to consolidate. This piece maps where each balancing authority in the West is heading – CAISO’s Extended Day-Ahead Market (EDAM), SPP’s Markets+, SPP’s RTO West expansion, and the Western Resource Adequacy Program (WRAP) run by the Western Power Pool – and what the resulting structure means for fuel mix and hub prices from the Pacific Northwest to the desert Southwest.
What Does the Western Interconnection Look Like Today?
WECC is the Regional Entity responsible for reliability planning and compliance monitoring and enforcement across the Western Interconnection, a footprint that runs from Alberta and British Columbia through 14 western US states to northern Baja California; WECC divested its own Reliability Coordinator function back in 2014 (WECC, “About WECC,” accessed September 21, 2026). The region still runs on roughly 38 separate balancing authorities – utilities and system operators each responsible for matching their own generation to their own load in real time, with CAISO the largest single BA at an estimated 35% of Western load (CAISO, “Balancing Authority,” accessed September 21, 2026).
The first crack in that fully bilateral structure was the Western Energy Imbalance Market (WEIM), the CAISO-run real-time imbalance market that by the May 2026 EDAM launch had grown to 22 participating entities across 11 states, covering an estimated 80% of Western electricity demand and delivering more than $8.6 billion in cumulative benefits since it began operating in 2014 (CAISO, “EDAM Is Live: PacifiCorp and CAISO Successfully Launch New Market May 1,” May 1, 2026). WEIM solved for real-time imbalances. It did not solve for day-ahead scheduling, and it did not touch resource adequacy at all – which is why four separate initiatives are now layered on top of it.
What Are the Four Moving Pieces Reshaping the West?
CAISO’s EDAM, SPP’s Markets+, SPP’s RTO West expansion and the Western Power Pool’s WRAP are frequently discussed as a single bundle of “Western market reform,” but they solve for different problems and are governed by different entities. EDAM and Markets+ compete for day-ahead scheduling; RTO West is a transmission and balancing-authority consolidation; WRAP is a resource adequacy program layered on top of whichever day-ahead market a utility ultimately picks.
The Four Western Market Initiatives
| Initiative | What it is | Status |
|---|---|---|
| CAISO EDAM | Voluntary day-ahead market extending CAISO’s existing day-ahead market to non-ISO Western utilities | Live May 1, 2026 with CAISO and PacifiCorp; expanding through 2028 (CAISO, May 1, 2026) |
| SPP Markets+ | Centralized day-ahead and real-time scheduling service for Western utilities that want a market without RTO membership | FERC approved the tariff January 16, 2025; targeted launch October 2027 (SPP, “Markets+,” accessed September 21, 2026; American Public Power Association, January 16, 2025) |
| SPP RTO West | Expansion of SPP’s RTO tariff into the Western Interconnection, with SPP taking on Reliability Coordinator duties for member utilities | FERC approved March 20, 2025; live April 1, 2026 (Utility Dive, March 21, 2025; SPP, “RTO Expansion,” accessed September 21, 2026) |
| WRAP (Western Power Pool) | Regional resource adequacy program combining a forward-showing obligation with an operational sharing pool; not a market | 16 entities committed to binding operations from winter 2027/2028, over 58,000 MW peak load (American Public Power Association, accessed September 21, 2026) |
EDAM’s participant list is growing on a set schedule: CAISO and PacifiCorp went live May 1, 2026, with Portland General Electric following in fall 2026, LADWP, the Balancing Authority of Northern California, PNM and Turlock Irrigation District committed for 2027, and Imperial Irrigation District joining in 2028 (CAISO, May 1, 2026). Markets+ has a different roster entirely – Bonneville Power Administration, Arizona Public Service, Salt River Project, Tucson Electric Power and seven more western entities committed as of October 27, 2025, targeting an October 2027 launch (SPP, “Markets+,” accessed September 21, 2026); the full roster appears in the FAQ below. The split is not incidental: Bonneville Power Administration picked Markets+ while PacifiCorp and Portland General Electric, also Pacific Northwest utilities, picked EDAM, so overlapping footprints will now be scheduled day-ahead by two different market operators.
RTO West is structurally different from either day-ahead market. Effective April 1, 2026, it linked SPP’s existing Eastern footprint to a new Western footprint via three direct-current interties totaling 510 MW (Utility Dive, March 21, 2025; SPP, “SPP and Member Utilities Successfully Complete Historic Western Expansion,” April 2, 2026). SPP now operates a consolidated SPP West Balancing Authority Area for these members – confirmed by SPP’s own FERC filing to let “the SPP West BAA” join the Northwest Power Pool’s reserve-sharing group, and by trade press describing it as the RTO’s new Western balancing authority area, which logged three energy emergency alerts in its first summer of operation (SPP, FERC Docket No. ER26-819-000, filed December 19, 2025; RTO Insider, “SPP Stakeholders Endorse Interim Solution for West BAA,” August 27, 2026). SPP’s own materials use no mirrored “East BAA” label, and the reason is physical rather than administrative: frequency is regulated separately in each asynchronous interconnection, so a single balancing authority area cannot span both. SPP’s eastern side is already consolidated. Its Integrated Marketplace, launched in 2014, “consolidated the SPP footprint’s 16 legacy Balancing Authorities into an SPP Balancing Authority” (SPP, “Markets and Operations,” accessed September 26, 2026). The 2026 expansion therefore added a second balancing authority on the western side rather than splitting an existing one, and SPP’s public materials describe the two footprints as separate regions for cost allocation, with an SPP East Region defined by zone, rather than as a matching pair (SPP, FERC Docket No. ER26-819-000, filed December 19, 2025). SPP’s published list runs to 25 entities joining or expanding their participation on April 1, 2026, of which nine led the expansion effort, across Arizona, Colorado, Montana, Nebraska, New Mexico, Utah and Wyoming. They include Basin Electric Power Cooperative, Tri-State Generation and Transmission, Northwestern Energy, Platte River Power Authority, Colorado Springs Utilities, Deseret Power Electric Cooperative, the Municipal Energy Agency of Nebraska and three Western Area Power Administration regions, Upper Great Plains, Colorado River Storage Project and Rocky Mountain (SPP, “RTO Expansion,” accessed September 26, 2026).
WRAP, run by the Western Power Pool, sits apart from all three. Asked directly whether WRAP is a capacity market, the Western Power Pool’s own description calls it “the first regional resource adequacy program in the history of the West” and structures it as a “regional reliability planning and compliance program,” not a market where capacity is bought and sold at a clearing price. It has two components: a forward-showing obligation, in which each participant demonstrates seven months ahead of a season that it holds sufficient capacity and deliverable transmission for its forecast peak, and an operational program, in which participants pool surplus capacity to cover deficits during tight hours on a week-ahead to day-ahead basis (Western Power Pool, “WRAP FAQs,” accessed September 21, 2026). Sixteen entities are committed to binding operations starting winter 2027/2028, representing more than 58,000 MW of peak load across the northwest, desert southwest, Canada and northern California (American Public Power Association, accessed September 21, 2026).
Noreva’s Power hub and Capacity hub track both sides of this split by ISO and zone; see Noreva’s EDAM launch-day briefing for a deeper read on the May 2026 go-live.
What Will the New Structure of Balancing Authorities Look Like?
This is the client question underneath all four initiatives, and the honest answer is that the roughly 38 balancing authorities WECC counts today are not consolidating into one structure – they are sorting into three.
Where Western Balancing Authorities Are Heading
| Footprint | Balancing authorities / utilities | Market type | Status |
|---|---|---|---|
| EDAM footprint | CAISO, PacifiCorp (PacE/PacW), PGE, LADWP, BANC, PNM, Turlock ID, Imperial ID | Each remains its own balancing authority; day-ahead scheduling centralized through CAISO’s market | Live May 1, 2026, expanding through 2028 (CAISO, May 1, 2026) |
| Markets+ footprint | BPA, APS, SRP, TEP, Puget Sound Energy, Tacoma Power, Chelan County PUD, Grant County PUD, Powerex, Tri-State G&T, Xcel/PSCo | Each remains its own balancing authority; day-ahead scheduling centralized through SPP’s market, without RTO membership | Committed as of October 27, 2025; targeted launch October 2027 (SPP, “Markets+,” accessed September 21, 2026) |
| SPP RTO West footprint | 24 entities including Basin Electric, Tri-State G&T (as an RTO member, distinct from its separate Markets+ commitment), Northwestern Energy, Platte River Power Authority, Colorado Springs Utilities, three WAPA regions (Upper Great Plains, Colorado River Storage Project, Rocky Mountain) | Individual balancing-authority status consolidates into a single SPP-operated West Balancing Authority Area | Live April 1, 2026; SPP West BAA confirmed via SPP’s own FERC filing and trade press (Utility Dive, March 21, 2025; SPP, FERC Docket No. ER26-819-000, December 19, 2025; RTO Insider, August 27, 2026) |
| Bilateral / uncommitted | Western utilities named neither to EDAM nor to the Markets+ Phase Two funding list: most notably NV Energy and Idaho Power, which CAISO describes as evaluating EDAM participation, and El Paso Electric (CAISO, May 1, 2026; SPP, Markets+ Phase Two funding entities as of October 27, 2025) | Continue trading bilaterally, potentially still inside WEIM for real-time imbalances | Ongoing |
Tri-State Generation and Transmission’s appearance in two rows is not a typo, and SPP’s own participant list explains it. Tri-State carries both of the markers SPP uses: it is one of the nine entities that initiated the western expansion effort, and it was already an SPP member before April 2026, expanding its participation rather than joining from outside (SPP, “RTO Expansion,” accessed September 26, 2026). It is separately a Markets+ Phase Two funding entity (SPP, Markets+ Phase Two funding entities as of October 27, 2025). A utility with load on both sides of the interconnection seam can hold an RTO membership on one side and a day-ahead market stake on the other without contradiction, which points to the layered nature of these commitments: RTO membership, market participation and resource-adequacy participation are three separate elections a utility can mix and match. Only RTO West members actually lose their status as a standalone balancing authority; EDAM and Markets+ participants keep their own BA identity and simply outsource day-ahead scheduling to a market operator, and WRAP participants keep their BA identity too while layering a seasonal resource-adequacy obligation on top, regardless of which day-ahead market they use. The seam that will matter most for congestion management sits between the EDAM and Markets+ footprints, where neighboring utilities – PacifiCorp and BPA in the Northwest, for instance – now schedule day-ahead through two different, non-identical market platforms rather than one.
What Will the Fuel Mix of This New Unified Market Structure Be?
The Western Interconnection’s underlying generation fleet does not change because of how it is scheduled – EDAM, Markets+, RTO West and WRAP all reorganize how existing generation clears a market, not what gets built – but the fuel mix each footprint brings to the table differs sharply by geography, and that shapes how the new seams will price. Two snapshots are worth holding side by side: the current fleet, taken from the generator inventory the EIA publishes every month, and the 2020 WECC-wide baseline still quoted in regional planning documents.
As of the August 2026 inventory, the balancing authorities that make up the US portion of the Western Interconnection operated about 298,000 MW of nameplate capacity across 6,023 generating units, or 282,000 MW on a net summer basis (Noreva analysis of EIA Form 860M, August 2026 generator inventory, accessed September 26, 2026).
US Western Interconnection operating capacity by resource, August 2026
| Resource | Nameplate capacity (MW) | Share of nameplate | Net summer capacity (MW) |
|---|---|---|---|
| Natural gas | 94,339 | 31.7% | 82,726 |
| Solar | 53,227 | 17.9% | 52,433 |
| Hydro (conventional) | 46,252 | 15.5% | 46,761 |
| Wind | 36,999 | 12.4% | 36,623 |
| Battery storage | 29,139 | 9.8% | 29,039 |
| Coal | 19,477 | 6.5% | 17,719 |
| Nuclear | 7,733 | 2.6% | 7,328 |
| Pumped storage | 4,720 | 1.6% | 4,979 |
| Geothermal | 3,774 | 1.3% | 2,531 |
| Biomass and waste | 1,563 | 0.5% | 1,377 |
| Petroleum and other | 688 | 0.2% | 561 |
| Total | 297,911 | 100% | 282,077 |
Battery storage does not appear at all in the 2020 WECC baseline below, and solar has roughly doubled its share of nameplate capacity since then, from about 8% to 17.9%. Storage now carries about 50% more nameplate capacity than coal, and solar close to 2.8 times as much. Both comparisons survive the move to net summer capacity, where storage and solar are rated at essentially their full nameplate figures while the gas fleet derates to 88% of its and coal to 91%. The ranking in the table is the same on either basis.
For comparison, on a wider footprint: as of 2020, WECC’s installed nameplate capacity of roughly 270,000 MW broke down as approximately 38% natural gas, 25% hydropower, 11% wind, 10% coal and 8% solar; annual generation between 2012 and 2018 ran close to 50% fossil-fueled, with hydropower contributing 24% to 30% depending on water year and solar’s share rising from under 1% to about 5% (Northwest Power and Conservation Council, 2021 Power Plan). That baseline covers all of WECC, including British Columbia, Alberta and northern Baja California, which the EIA inventory does not, so the 2020 hydro and gas shares are not measured on the same footprint as the 2026 table. Treat the differences between the two as directional rather than as a measured change.
Layered onto that baseline, the resource mix differs by footprint. The EDAM side leans on Pacific Northwest hydro (PacifiCorp, PGE) and California solar and storage (CAISO, LADWP, Imperial ID), plus the 2,323 MW of nuclear at Diablo Canyon and, once PNM joins in 2027, New Mexico wind and solar. The Markets+ side leans on Columbia and Snake River hydro through BPA, desert Southwest gas and solar through APS, SRP and TEP, and the two large nuclear stations on that side of the seam: the 1,200 MW Columbia Generating Station in Washington, whose output BPA markets, and the three units of the Palo Verde Generating Station in Arizona, 4,210 MW combined, which Arizona Public Service describes as the nation’s largest power producer of any kind for more than 25 years, a claim that rests on annual output rather than installed capacity (APS, “Nuclear Generation,” accessed September 21, 2026; unit capacities from Noreva analysis of EIA Form 860M, August 2026 generator inventory, accessed September 26, 2026). Those two stations, plus Diablo Canyon on the EDAM side, are the whole of the US Western Interconnection’s nuclear fleet: three stations, six units, 7,733 MW. Columbia and Diablo Canyon have a single owner each, Energy Northwest and Pacific Gas and Electric, so each sits squarely inside one market. Palo Verde does not. Its seven owners split across the seam: Arizona Public Service holds 29.10% and Salt River Project 17.49%, both Markets+ funding entities, for 46.59% on the Markets+ side; Southern California Edison holds 15.80%, the Los Angeles Department of Water and Power 5.70% and Public Service Company of New Mexico 10.20%, all inside CAISO or scheduled to join EDAM in 2027, for 31.70% on the CAISO and EDAM side; the Southern California Public Power Authority holds a further 5.91% on behalf of California municipal members; and El Paso Electric holds 15.80% without being named to either market (EIA Form 860, Schedule 4 ownership file, 2025 data year, accessed September 26, 2026). The second-largest generating station in the US Western Interconnection, behind only the 6,809 MW Grand Coulee dam, will therefore have its output split across two competing day-ahead markets, with a further 21.71% held by owners named to neither: El Paso Electric at 15.80% and the Southern California Public Power Authority at 5.91%. SPP RTO West brings in the mountain-west wind corridor – Wyoming, Montana, Colorado – through Northwestern Energy, Tri-State and Platte River, plus coal capacity still running in that corridor; WECC-wide coal capacity stood at just under 35 GW in 2019 and is projected to decline by more than 20 GW between 2019 and 2030 (Northwest Power and Conservation Council, 2021 Power Plan); the US portion of the interconnection was down to 19,477 MW by August 2026, consistent with that path, though the 2026 figure covers the US side only and the 2019 baseline included Alberta, so the two are not like-for-like (Noreva analysis of EIA Form 860M, August 2026 generator inventory, accessed September 26, 2026).
The practical read for asset owners: EDAM’s footprint is increasingly hydro-and-solar coincident, which tends to compress midday prices and steepen evening ramps; Markets+ and RTO West bring more thermal and wind diversity into their combined footprint, which should dampen some of that duck-curve volatility for participants on that side of the seam – but the two day-ahead markets will not co-optimize across each other, so the basis between them becomes a new variable rather than an old one disappearing.
How Does This Reshape Prices and Capacity Value Across the West?
WRAP’s binding forward-showing obligation, once it takes effect for winter 2027/2028, is the first time firm capacity gets priced across a wide swath of the West on a consistent, region-wide basis rather than utility by utility, even though WRAP itself is explicitly not a market-clearing mechanism (Western Power Pool, “WRAP FAQs,” accessed September 21, 2026). For hub pricing, the EDAM/Markets+ split changes who sets marginal price where. NP15 and SP15 basis inside California will increasingly reflect EDAM-wide congestion once PGE, LADWP, BANC, PNM and Turlock ID are all clearing through the same day-ahead engine as CAISO. Mid-Columbia (Mid-C), the Pacific Northwest’s principal hydro trading hub, sits at the seam itself: PacifiCorp and PGE clear through EDAM while BPA, which markets the federal hydro system on the river, clears through Markets+, so Mid-C basis behavior after 2027 will depend on how two separate day-ahead markets handle transfers across that boundary. No observed basis figure can exist yet for a boundary that only takes effect in 2027. What can be modeled is a forward view, and that is what Noreva’s Western forward curves are built to produce as the participant schedule firms up. Palo Verde, the desert Southwest’s reference hub, sits inside the Markets+ and RTO West footprint via APS and SRP, while remaining a delivery point for California load-serving entities, which together hold 27.41% of the plant, Southern California Edison at 15.80%, the Southern California Public Power Authority at 5.91% and the Los Angeles Department of Water and Power at 5.70%, and which schedule either inside CAISO or, from 2027, through EDAM.
Noreva’s coverage today reflects where these markets stand, per Noreva’s coverage status, September 2026: CAISO resource adequacy and SPP capacity forecasts are live and cover the pre-EDAM and pre-Markets+ baseline; CAISO’s NP15 and SP15 hubs and the Pacific Northwest’s Mid-C hub are coming soon in Noreva’s forward-curve coverage as EDAM and Markets+ price history accumulates. Noreva has also argued that thermal buildout, not scarcity pricing, is increasingly the swing factor in SPP’s own capacity outlook – see “Can Gas Save SPP?” and “Dispatchable Dominance in SPP and MISO” – a dynamic that will extend into the RTO West footprint as its gas queue clears.
Frequently Asked Questions
In the context of WECC, WRAP and SPP RTO West expansion and Markets+, what will be the new structure of balancing authorities?
SPP RTO West members give up individual balancing-authority status and consolidate into a single SPP-operated West Balancing Authority Area, confirmed via SPP’s own FERC filing and trade press (SPP, FERC Docket No. ER26-819-000, December 19, 2025; RTO Insider, August 27, 2026). EDAM and Markets+ participants keep their own balancing-authority status and instead centralize day-ahead scheduling through CAISO’s or SPP’s respective markets. WRAP participants keep their BA status too and layer a binding seasonal resource-adequacy obligation on top, independent of which day-ahead market they use (CAISO, May 1, 2026; Western Power Pool, “WRAP FAQs,” accessed September 21, 2026).
What will be the fuel mix of this new unified market structure?
There is no single unified fuel mix – the structure is two day-ahead markets plus one consolidated RTO, each drawing on a different resource base. EDAM’s footprint leans on Pacific Northwest hydro and California solar and storage. Markets+’s footprint leans on Columbia and Snake River hydro through BPA, desert Southwest gas and solar, and the Palo Verde and Columbia Generating Station nuclear plants. SPP RTO West’s footprint adds mountain-west wind and remaining coal capacity across Wyoming, Montana and Colorado. Across the US portion of the Western Interconnection, the August 2026 generator inventory gives about 298,000 MW of nameplate operating capacity: 31.7% natural gas, 17.9% solar, 15.5% hydro, 12.4% wind, 9.8% battery storage, 6.5% coal and 2.6% nuclear, with pumped storage, geothermal, biomass and oil making up the remaining 3.6% (Noreva analysis of EIA Form 860M, August 2026 generator inventory, accessed September 26, 2026). Battery storage now exceeds coal on a nameplate basis. The wider WECC baseline, which also covers British Columbia, Alberta and northern Baja California, was roughly 38% gas, 25% hydro, 11% wind, 10% coal and 8% solar as of 2020, with coal capacity projected to decline by more than 20 GW between 2019 and 2030 (Northwest Power and Conservation Council, 2021 Power Plan).
Which utilities are joining EDAM versus Markets+?
EDAM: CAISO and PacifiCorp (live May 1, 2026); Portland General Electric (fall 2026); LADWP, the Balancing Authority of Northern California, PNM and Turlock Irrigation District (2027); Imperial Irrigation District (2028). Markets+: Bonneville Power Administration, Arizona Public Service, Salt River Project, Tucson Electric Power, Puget Sound Energy, Tacoma Power, Chelan County PUD, Grant County PUD, Powerex, Tri-State Generation and Transmission, and Xcel Energy’s Public Service Company of Colorado, the Markets+ Phase Two funding entities as of October 27, 2025, targeting an October 2027 launch (CAISO, May 1, 2026; SPP, “Markets+,” accessed September 21, 2026).
Is the Western Resource Adequacy Program a capacity market?
No. The Western Power Pool describes WRAP as “the first regional resource adequacy program in the history of the West,” structured as a regional reliability planning and compliance program rather than a market with a clearing price. It combines a forward-showing obligation – participants prove seven months ahead of a season that they hold sufficient capacity and deliverable transmission – with an operational program that pools surplus capacity to cover deficits during tight hours. Sixteen entities are committed to binding operations starting winter 2027/2028, representing more than 58,000 MW of peak load (Western Power Pool, “WRAP FAQs,” accessed September 21, 2026; American Public Power Association, accessed September 21, 2026).
How is SPP RTO West different from SPP Markets+?
RTO West consolidates member utilities’ balancing-authority status into a single SPP-operated West Balancing Authority Area, effective April 1, 2026. Markets+ is narrower – a day-ahead and real-time scheduling service SPP sells to utilities that want market access without joining the RTO or surrendering their own balancing-authority status, targeted to launch in October 2027. Some entities, including Tri-State, appear in both programs but in different capacities (SPP, “RTO Expansion” and “Markets+,” accessed September 21, 2026; SPP, FERC Docket No. ER26-819-000, December 19, 2025).
Get the Forward Curve Behind the New Western Footprint
Noreva tracks CAISO and SPP resource adequacy today, per Noreva’s coverage status, September 2026, with NP15, SP15 and Mid-C hub coverage coming soon as EDAM and Markets+ price history builds. Noreva’s methodology links transaction-level pricing insight to the fundamentals shifting under WECC, WRAP, EDAM, Markets+ and RTO West.
Book a demo to see Noreva’s Western power and capacity forecasts by ISO and zone.
CONTACT US
Ready to Price the Future?
Book a demo to see the platform in action or speak directly with an analyst about your specific use-case.